Milestones & tasks

🏁 Design and plan
11/22/25 - 1/8/26
#1 · Architect design Completed
Start: 12/15/25
End: 12/31/25
设计和画图
#2 · Structual design Completed
Start: 12/23/25
End: 1/3/26
#3 · 提交permit Completed
Start: 1/8/26
End: 1/8/26
🏁 Demolition
12/12/25 - 1/8/26
#1 · 拆屋内墙顶的popcorn Completed
整屋墙顶的popcorn
#2 · Demo floor Completed
#3 · Demo all cabinets Completed
🏁 Permits & Approvals
1/8/26 - 3/29/26
#1 · Review cycle 1 Completed
Start: 1/8/26
End: 2/12/26
#2 · Modify and resubmit Completed
Start: 2/12/26
End: 2/24/26
#3 · Receive approval Completed
Start: 3/26/26
🏁 Foundation
3/29/26 - 4/16/26
#1 · 加固foundation Completed
Start: 3/29/26
End: 4/5/26
针对structure的修改
#2 · Foundation inspection Completed
Start: 4/12/26
End: 4/12/26
City
#3 · 灌水泥 Completed
Start: 4/13/26
End: 4/16/26
🏁 Framing
4/12/26 - 4/16/26
#1 · Main entrance ceiling raising New
#2 · Hallway ceiling raising New
#3 · 开dining room一扇门 New
将连接到family room的墙打通,做一个门
#4 · 主卧入室门位置变更 New
#5 · family room和living room通向后院的玻璃门更换 New
🏁 Roughing
4/19/26 - 5/14/26
#1 · 重整水管 New
#2 · Install AC and heat-pump New
#4 · Re-wiring New
重整电线,装插座
🏁 Insulation & Drywall
5/17/26 - 5/21/26
#1 · 室内加molding New
Window, crown
#2 · 墙面做level 4 New
除了卫生间和厨房的墙面
#3 · 墙内隔温层检查更换 New
insulation layer inside the wall
🏁 Interior Finishes
5/24/26 - 6/4/26
#1 · 主卧卫生间重做 New
将目前卫生间边上的closet和furnace room推掉,并入
#2 · 次卧卫生间重搞 New
结构基本不变,看对比图
#3 · 客厅的壁炉拆掉 New
客厅墙角到烟囱
#5 · 厨房remodel New
1. 将一面门拆掉,补上墙 2. 将一面墙的窗口补上 3. 拆掉与dining room连接的短墙 4. 拆装橱柜 5. 窗户改装 6. 水池移位
#6 · 换整屋地板 New
Remove the current floor; install engineering floor and baseboard
#7 · Enhance family room fireplace New
修整当前的壁炉,无需拆
#8 · 三卧稍作调整 New
#9 · 次卧稍作调整 New
看对比图
🏁 Fixtures & Final Connections
6/7/26 - 6/11/26
#1 · Install recessed lights New